CDOT Wacker Drive

The Wacker Drive Viaduct Utility Relocation Project consisted of the removal and installation of the storm sewer and the combined sewer, removal and installation of water mains, placement of approximately 200 feet of “UTILIDOR” conveyance, placement of a CTA/City Electric Duct Bank and traffic signal modernization.

Ardmore inspected work of the private contractor constructing 24 inch sanitary sewer, 30 inch storm sewer, complete with manholes and poured in place reinforced concrete structures and insured that work was constructed to plans and specifications.

Additionally, Ardmore inspected construction of water mains from 8 inch to 24 inches, monitored pressure tests; insured that work was performed to contract plans and specifications. Inspected construction of 6 inch temporary concrete pavement over trenches of completed work.